Stacks Image 657

Alta Westover Hills

Where: San Antonio, TX
Who: Wood Partners
How Much: ~$38 Million
What: 351-unit “iSmart”-branded Garden Style Workforce Housing Project
When: Q4 2024 Commencement

VP of Construction responsible for program- and design-management along with consultant team, Project Executive, Project Manager, and other Wood Partners stakeholders for this $38MM 3-story garden style apartment development in San Antonio, TX.




Stacks Image 785

Alta Ed Schmidt

Where: Hutto, TX
Who: Wood Partners
How Much: >$200 Million
What: 1400+/- unit “iSmart”-branded Garden Style Workforce Housing Project
When: Q1 2025 Commencement

VP of Construction responsible for program- and design-management along with consultant team, Project Executive, Project Manager, and other Wood Partners stakeholders for this multi-phase $100MM+ 3-story garden style apartment development east of Austin in Bastrop, TX.




Stacks Image 777

Alta Westinghouse Townhomes

Where: Georgetown, TX
Who: Wood Partners
How Much: ~$38 Million
What: 168-unit Townhome Project
When: Q2 2025 Completion

VP of Construction responsible for program- and design-management along with consultant team, Project Executive, Project Manager, and other Wood Partners stakeholders for this $38MM Townhome apartment development in Georgetown, TX.




Stacks Image 793

Alta Trails Apartments

Where: Bastrop, TX
Who: Wood Partners
How Much: >$100 Million
What: 700+/- unit “iSmart”-branded Garden Style Workforce Housing Project
When: Q3 2025 Completion

VP of Construction responsible for program- and design-management along with consultant team, Project Executive, Project Manager, and other Wood Partners stakeholders for this multi-phase $100MM+ 3-story garden style apartment development east of Austin in Bastrop, TX.




Stacks Image 769

Alta Rolling Oaks Apartments

Where: San Antonio, TX
Who: Wood Partners
How Much: ~$48 Million
What: 366-unit “iSmart”-branded Garden Style Workforce Housing Project
When: Q3 2024 Completion

VP of Construction responsible for leading a team consisting of the General Superintendent, Superintendent, Project Executive, Project Manager, Assistant Project Manager, and Assistant Superintendents for this $48MM 3-story garden style apartment development in San Antonio, TX.




Stacks Image 761

Alta Center Point Apartments

Where: San Marcos, TX
Who: Wood Partners
How Much: ~$45 Million
What: 330-unit “iSmart”-branded Garden Style Workforce Housing Project
When: Q3 2024 Completion

VP of Construction responsible for leading a team consisting of the General Superintendent, Superintendent, Project Executive, Project Manager, Assistant Project Manager, and Assistant Superintendents for this $45MM 3-story garden style apartment development in San Marcos, TX.




Stacks Image 753

Alta Wildhorse Ranch

Where: Austin, TX
Who: Wood Partners
How Much: ~$52 Million
What: 257-unit Townhome-For-Rent Community; 25 buildings; 10 units in 3-story clubhouse building
When: Q3 2024 Completion

VP of Construction responsible for leading a team consisting of the General Superintendent, Superintendent, Project Executive, Senior Project Manager, Assistant Project Manager, and Assistant Superintendents for this $52MM Townhome apartment development in East Austin near the Tesla plant.




Stacks Image 628

The Albright

Where: Austin, TX
Who: Wood Partners
How Much: ~$45 Million
What: 266-unit 5-story Wrap w/ Precast Garage
When: Q3 2024 Completion

VP of Construction responsible for leading a team consisting of the General Superintendent, Superintendent, Project Executive, Project Manager, Assistant Project Manager, and Assistant Superintendents for this $45MM 5-story wrap in North Central Austin.




Stacks Image 745

Alta Berry Creek Apartments

Where: Georgetown, TX
Who: Wood Partners
How Much: ~$36 Million
What: 300-unit “iSmart”-branded Garden Style Workforce Housing Project
When: Q4 2023 Completion

VP of Construction responsible for leading a team consisting of the General Superintendent, Superintendent, Project Executive, Project Manager, Assistant Project Manager, and Assistant Superintendents for this $36MM 3-story garden style apartment development in Georgetown, TX.




Stacks Image 737

Alta Blue Goose Apartments

Where: Austin, TX
Who: Wood Partners
How Much: ~$33 Million
What: 300-unit “iSmart”-branded Garden Style Workforce Housing Project
When: Q4 2023 Completion

VP of Construction responsible for leading a team consisting of the General Superintendent, Superintendent, Project Executive, Project Manager, Assistant Project Manager, and Assistant Superintendents for this $33MM 3-story garden style apartment development in East Austin near the Tesla plant.




Stacks Image 729

Alta Leander Station Apartments

Where: Leander, TX
Who: Wood Partners
How Much: ~$32 Million
What: 276-unit “iSmart”-branded Garden Style Workforce Housing Project
When: Q1 2023 Completion

VP of Construction responsible for leading a team consisting of the General Superintendent, Superintendent, Sr. Project Manager, Project Manager, Assistant Project Manager, and Assistant Superintendents for this $32MM 3-story garden style apartment development in Leander, TX.




Stacks Image 721

Alta Austin Ave Apartments

Where: Georgetown, TX
Who: Wood Partners
How Much: ~$32 Million
What: 312-unit “iSmart”-branded Garden Style Workforce Housing Project
When: Q4 2022 Completion

VP of Construction responsible for leading a team consisting of the General Superintendent, Superintendent, Sr. Project Manager, Project Manager, Assistant Project Manager, and Assistant Superintendents for this $32MM 3-story garden style apartment development near Georgetown High School, in Georgetown, TX.




Stacks Image 713

Alta Cathedral Lakes Apartments

Where: Spring, TX
Who: Wood Partners
How Much: ~$32 Million
What: 300-unit “iSmart”-branded Garden Style Workforce Housing Project
When: Q3 2021 Completion

VP of Construction responsible for leading a team consisting of the Sr. Superintendent, Superintendent, Regional Construction Manager, Project Manager, Assistant Project Manager, and Assistant Superintendents for this $32MM 3-story garden style apartment development near the Woodlands in Spring, TX.




Stacks Image 705

Alta River Oaks Apartments

Where: Houston, TX
Who: Wood Partners
How Much: ~$56 Million
What: 364-unit 5/1+ Podium w/ CIP Garage
When: Q2 2022 Completion

Regional Construction Manager responsible for leading a team consisting of the Sr. Superintendent, Superintendent, Sr. Project Manager, Project Manager, Assistant Project Manager, and Assistant Superintendents for this $56MM 5-story podium apartment near Memorial Park.




Stacks Image 697

Alta West Alabama Apartments

Where: Houston, TX
Who: Wood Partners
How Much: ~$41 Million
What: 304-unit 5-story Wrap w/ Precast Garage
When: Q2 2021 Completion

Regional Construction Manager responsible for leading a team consisting of the Sr. Superintendent, Superintendent, Sr. Project Manager, Project Manager, Assistant Project Manager, and Assistant Superintendents for this $41MM 5-story wrap apartment near River Oaks Park.




Stacks Image 689

Alta Washington Apartments

Where: Houston, TX
Who: Wood Partners
How Much: ~$34 Million
What: 204-unit, 5/3 Podium with CIP Garage + 6 Townhomes
When: Q2 2021 Completion

Regional Construction Manager responsible for leading a team consisting of the Sr. Superintendent, Superintendent, Sr. Project Manager, Project Manager, Assistant Project Manager, and Assistant Superintendents for this $34MM 5-story podium apartment near Memorial Park.




Stacks Image 681

Alta Med Main Apartments

Where: Houston, TX
Who: Wood Partners
How Much: ~$42 Million
What: 338-unit, 4-Story Wrap Apartment Building with Precast Garage
When: Q2 2021 Completion

Regional Construction Manager responsible for leading a team consisting of the Sr. Superintendent, Superintendent, Sr. Project Manager, Project Manager, Assistant Project Manager, and Assistant Superintendents for this $42MM 4-story wrap apartment near NRG Stadium.




Stacks Image 673

Alta Baytown Apartments

Where: Houston, TX
Who: Wood Partners
How Much: ~$34 Million
What: 3-story, 336-unit Garden Apartment
When: Q1 2021 Completion

Regional Construction Manager responsible for leading a team consisting of the Sr. Superintendent, Superintendent, Sr. Project Manager, Project Manager, Assistant Project Manager, and Assistant Superintendents for this $34MM 3-story garden style apartment development east of Houston, in Baytown, TX.




Stacks Image 649

[Alta Trailhead Apartments](

Where: Austin, TX
Who: Wood Partners
How Much: ~$38 Million
What: 3-story, 308-unit Urban Garden Apartment
When: Q1 2021 Completion

Regional Construction Manager responsible for leading a team consisting of the Superintendent, Project Manager, Assistant Project Manager, and Assistant Superintendents for this $38MM 3-story urban garden style apartment development on the up-and-coming East Side of Austin.




Stacks Image 641

Alta Tech Ridge Apartments

Where: Austin, TX
Who: Wood Partners
How Much: ~$25 Million
What: 3-story, 276-unit Luxury Apartment
When: Q1 2019 Completion

SPM responsible for building and leading a team consisting of the Superintendent, Project Manager, and Assistant Superintendents for this $25MM 3-story garden-style apartment development in the Tech Ridge area of north Austin. My team assisted our development team with the creation of new building finish standards for the Austin market, prepared the GMP, and conducted all forecasting, budget reporting, subcontract management, and change management. I also supervise the field team with respect to schedule, quality control, and safety.




Stacks Image 454

Cooper Villas Apartments

Where: Austin, TX
Who: IMPACT Developers
How Much: ~$6 Million
What: 41-unit Townhome Community
When: Fall 2016

VP responsible for building and leading a team consisting of the General Superintendent, Superintendent, Project Manager, and Assistant PM for this $6MM 2-story townhome development in central South Austin. Oversight of all forecasting, budget reporting, subcontract management, and change management. Also responsible for managing the field team with respect to schedule, quality control, and safety.




Stacks Image 621

Trillium Terrace Apartments

Where: Austin, TX
Who: IMPACT Developers
How Much: ~$15 Million
What: 3-story, 168-unit Luxury Apartment
When: Fall 2016 Completion

VP responsible for building and leading a team consisting of the General Superintendent, Superintendent, Project Manager, and Assistant PM for this $15MM 3-story garden-style apartment building in central South Austin. Oversight of all forecasting, budget reporting, subcontract management, and change management. Also responsible for managing the field team with respect to schedule, quality control, and safety.




Stacks Image 612

Rivera Apartments

Where: San Antonio, TX
Who: Argyle Residential
How Much: ~$28 Million
What: 4-story, 302-unit Luxury Apartment
When: Spring 2016 Completion

Sr. Project Manager overseeing the on-site team for this ~$28MM podium/wrap apartment project in Austin. Led a team of assistant project managers, project engineers, superintendents, assistant superintendents, and punch/finish carpenters with oversight responsibility for all forecasting, budget reporting, subcontracting, change management, and project monthly reporting.




Stacks Image 460

Lakeshore Azul Apartments

Where: Austin, TX
Who: Argyle Residential
How Much: ~$28 Million
What: 5-story, 295-unit Luxury Apartment
When: Summer 2015 Completion

Sr. Project Manager overseeing the on-site team for this ~$28MM podium/wrap apartment project in Austin. Led a team of assistant project managers, project engineers, superintendents, assistant superintendents, and punch/finish carpenters with oversight responsibility for all forecasting, budget reporting, subcontracting, change management, and project monthly reporting.




Stacks Image 88

Temple Beth Shalom

Where: Austin, TX
Who: Temple Beth Shalom Congregation
How Much: ~$6 Million
What: 21,000sf Jewish Temple and Community Center
When: Summer 2013 Completion

Project lead on the $5.5MM ground-up construction of this Andersson-Wise-designed temple and community center on the Dell Jewish Community Center in northwest Austin. Led a small team with oversight responsibility for all forecasting, budget reporting, subcontracting, change management, and project monthly reporting.




Stacks Image 291

Bramasol Custom Residence

Where: Bay Area, CA
Who: Confidential Owner
How Much: $30+ Million
What: 16,250sf Custom Residence
When: Spring 2012 Completion

Lead Project Manager reporting to the Project Director and Project Sponsor. In charge of the financial management of this ultra-high-end custom residence designed by William R. La Voie Architect, including oversight responsibility for all forecasting, budget reporting, subcontracting, change management, preparation of monthly payment applications, and project monthly reporting.

Stacks Image 299

Park Terrace Condominiums

Where: San Francisco, CA
Who: 5th & Berry, LLC
How Much: $54 Million
What: 7-Story, 110-unit condominium and townhouse development
When: August 2007 – On-time, below-budget completion of the shell building. 100% on-time delivery of individual units to owners.

Responsible for managing the interior build-out for the shell building as well as the unit interiors options and upgrades program; design and budget oversight for the interior scopes; managed the interior project schedule as it related to the master project schedule; developed and enforced individual work plans for each of 110 units based on escrow closing dates; oversaw the work order subcontracting for each unit.




Stacks Image 295

Opus Logistics Center - Building 9

Where: Stockton, CA
Who: Fresh and Easy Neighborhood Market
How Much: ~$60 Million
What: ~750,000sf Industrial Distribution Center and Site Improvements
When: April 2009 – Building substantially completed and turned over to owner 4 weeks ahead of schedule and $1 million under budget

Led the team responsible for managing the design, entitlement, buyout and construction of the tenant improvement requirements for this 750,000sf concrete tilt-up building; implemented new project collaboration system for the entire design-build team, including internal and external consultants, owner’s representatives, and subcontractors; managed the subcontracting, budget, procurement, and change processes for the interior systems work; provided oversight and review of the subordinates’ work.




Stacks Image 504

Opus Logistics Center - Building 3

Where: Stockton, CA
Who: Arch Road Limited Partnership LLC
How Much: $13 Million
What: ~388,000sf Industrial Distribution Center and Site Improvements
When: December 2008 – On-time, below-budget completion of the shell building.

Responsible for entitlement and buyout process; primary interface with ownership team; managed internal and external consultants; prepared feasibility analyses for several alternate designs for build-to-suit clients. I managed this project briefly from January 2008 to April 2008, until I was reassigned to the more critical Arch Road Building #9, a complex build-to-suit for a high-profile client.




Jacuzzi Ranch Retail

Where: Antioch, CA
Who: Opus West Corp.
How Much: $60 Million
What: ~450,000sf Retail Power Center on 50 acres
When: December 2007 – Go / No-Go decision Comments: Due to shifting market conditions for retail development, this project was put on hold at the conceptual design stage.

Led entitlement process; met with internal and external stakeholders; prepared conceptual estimates, schedules, and project pro formas; managed external design consultants in preparation of master site plans and survey documents.




Stacks Image 301

The Village at Sacramento Gateway

Where: Sacramento, CA
Who: Opus West Corp.
How Much: $13 Million
What: Lifestyle Retail Center comprised of seven separate wood-framed multi-tenant buildings, public gathering areas and site improvements.
When: September 2006 – On-time, below-budget completion of all seven buildings, including TIs, which enabled Opus to complete the $150-million sale of the master-planned Sacramento Gateway retail project.

Managed from conception to completion all aspects of this lifestyle retail center in Sacramento, CA, including construction of all shell buildings, TIs, coordination with tenants and project owner, budget and schedule reporting. Managed interns and oversaw work of administrative assistant in the field.

Tenants included PacSun, Tilly’s Surf Shop, Ground Zero Board Shop, Starbucks, Qdoba, Beach Hut Deli, Aeropostale, American Eagle Outfitters, Lids, Claire's, Sports Clips, Mizu Sushi.




Stacks Image 303

The Promenade at Sacramento Gateway

Where: Sacramento, CA
Who: Opus West Corp.
How Much: ~$90 Million
What: 90-acre retail power center comprised of approximately 550,000sf of concrete tilt-up and 150,000 of CMU big-box stores, and 50,000sf of wood-framed shop buildings.
When: December 2005 – On-time, below-budget completion of all buildings, including TIs, which enabled us to begin The Village ahead of schedule.

Full-time on-site APM responsible for design management, submittal and RFI management, change management for entire project (except for the 50,000sf of shops). Lead PM on three TIs totaling ~60,000sf, including budget and schedule responsibility. Managed interns and oversaw work of administrative assistant in the field.

Tenants included Barnes & Noble, Old Navy, ULTA, Target, Cost Plus World Market, Linen’s N Things (later replaced by Bed Bath and Beyond), Pier 1, Sports Authority, Sam’s Club, Men’s Wearhouse, Justice for Girls, Pei Wei, Best Buy, Office Depot, and BevMo!.




Stacks Image 305

Opus Corporate Center

Where: Roseville, CA
Who: Opus West Corp.
How Much: Various
What: Various Tenant Improvements in 120,000sf Class A Office Building
When: 2004

Coordinated design, prepared budgets and issued contracts for several Class A office tenant improvement projects.




River Storage Expansion

Where: Isleton, CA
Who: Glenn Giavannoni
What: Expansion of existing boat and RV storage facility.
When: Completed in 2004

Lead designer for project. Responsible for client relationship and overall management of entitlement, design and documentation.




Stacks Image 307

Rio Vista Ford Building

Where: Rio Vista, CA
Who: Ken Adgate / Rio Vista Ford
What: ~$2 Million Auto Dealership in Rio Vista, CA, including site improvements, public rights-of-way and new showroom/offices and renovations to existing showroom.
When: Completed in 2004

Lead design engineer for project. Responsible for client relationship and overall management of entitlement, design and documentation.




Stacks Image 309

Awender Medical Office Building

Where: Rio Vista, CA
Who: Dr. Joseph Awender
What: Structural rehabilitation of 70-yr old 5,000sf unreinforced brick building.
When: Completed in 2004

Lead designer for project; responsible for overall management of design and documentation; project required removal of existing ceiling to unload roof trusses so they could be rebuilt, and installation of structural steel frame system to distribute lateral loads away from unreinforced wall.




Coast Guard Island Launch Ramp

Where: Alameda, CA
Who: USCG
What: Addition of new heavy-duty mission-critical launch ramp facility over existing obsolete ramp.
When: Completed in 2004

Lead designer for project; responsible for overall management of design and documentation; project required working around existing work-in-place, tying in new ramp to existing approach area; solution required installation of vertically cantilevered steel piles with pre-cast ramp deck panels capable of accommodating the Coast Guard’s heaviest trailered vessels.




FiberDocks Engineering Report

Who: FiberDocks / Jerrie Giavannoni
When: 2004
What: Prepared engineering report and specifications for proprietary fiber-reinforced floating dock system.




Stacks Image 311

Rehrmann Residence

Where: Isleton, CA
Who: Rehrmann Family
What: $1+ million custom residence in Isleton, CA on large waterfront property overlooking the Sacramento River.
When: Completed in 2004

Lead engineer for project. Responsible for interpreting Architect’s conceptual designs, client relationship and overall management of entitlement, design and documentation.




Maddox Residence

Where: Isleton, CA
Who: Paul Maddox
What: ~$500,000 custom residence in Isleton, CA on large waterfront property overlooking the Georgiana Slough.
When: Completed in 2004

Lead engineer for project. Responsible for interpreting Architect’s conceptual designs, and overall management of entitlement, design and documentation.




Stacks Image 313

City of Isleton Waterfront Improvement

Where: Isleton, CA
Who: City of Isleton / Sacramento Redevelopment Agency (SRA)
What: ~$2 Million public facility in Isleton, CA, including site improvements, public restrooms, vessel docking, and fishing pier.
When: Completed in 2003

Lead design engineer for project; responsible for client relationship and overall management of entitlement, design and documentation; construction administrator for City of Isleton; primary interface between City and subcontractors / consultants / SRA personnel.




RD38 Trash Rack

Where: Isleton, CA
Who: Bureau of Reclamation: District 38
What: Widening of district irrigation canal and addition of trash rack facility.
When: Completed in 2003

Lead designer for project. Responsible for client relationship and overall management of design and documentation.




Newcastle Monopole, Oakland Cell Tower Addition, et al

Where: Various
Who: Advanced Design Consultants (on behalf of Cingular Wireless, now AT&T Wireless)
What: Design of several cellular tower structures, including steel monopoles and equipment platforms.
When: Various from 2001 to 2003

Lead designer for projects. Responsible for client relationship and overall management of entitlement, design and documentation.




Deak Residence

Where: Isleton, CA
Who: Joseph Deak Family
What: ~$600,000 custom residence on waterfront property overlooking the Georgiana Slough.
When: Completed in 2003

Lead designer for project. Responsible for interpreting Architect’s conceptual designs, client relationship and overall management of entitlement, design and documentation.




Dahlke Addition

Where: Lodi, CA
Who: Dahlke Family
What: 2-story garage and apartment addition to private residence.
When: Completed in 2003

Lead designer for project. Responsible for client relationship and overall management of entitlement, design and documentation.




Kerber Addition

Where: Lodi, CA
Who: Kerber Family
What: 2-story garage and apartment addition to private residence in Lodi, CA.
When: Completed in 2003

Lead designer for project. Responsible for client relationship and overall management of entitlement, design and documentation.




Gibbs Rehabilitation

Where: Oakland, CA
Who: Robert Gibbs
What: 2-story garage and apartment addition to private residence.
When: Completed in 2003

Lead designer for project; responsible for client relationship and overall management of entitlement, design and documentation.




Uhalt Residence

Where: Isleton, CA
Who: Uhalt Family
What: ~$800,000 custom residence on large waterfront property overlooking the Sacramento River.
When: Completed in 2002

Lead engineer for project. Responsible for interpreting Architect’s conceptual designs, and overall management of entitlement, design and documentation.




Leone Residence

Where: Rio Vista, CA
Who: Val Leone
What: 16’ tall structural steel foundation for private residence on large waterfront property overlooking the San Joaquin River.
When: Completed in 2002

Lead designer for project. Responsible for client relationship and overall management of entitlement, design and documentation.




Giles Residence

Where: Isleton, CA
Who: Giles Family
What: 14’ tall structural steel foundation for private residence on large waterfront property.
When: Completed in 2002

Lead designer for project. Responsible for client relationship and overall management of entitlement, design and documentation.




West Coast Docks Engineering Report

Where: Walnut Grove, CA
Who: West Coast Docks / J.B. Morias
What: Prepared engineering report and specifications for proprietary aluminum frame floating dock system.
When: 2002




Kirkeby Remodel

Where: San Anselmo, CA
Who: Stefan Kirkeby
What: ~$300,000 addition and remodel to existing ~$500,000 home.
When: Completed in 2002

Lead engineer for project. Responsible for client relationship and overall management of entitlement, design and documentation.